During the 2003 and 2006 Municipal Elections, we heard loud and clear that Trent Hills residents wanted their infrastructure repaired. To this end, we have done just that. Each year we have made significant headway in recapturing waste-water treatment capacity in Campbellford by continuing with our sewer speration programs. Our rural roads continue to rise in their condition index, and some previous gravel roads are now surface treated. Our downtowns continue to improve with new sidewalks, pavement, and energy efficient street lighting. Our Community Improvement Plan is starting to reflect our successful partnerships with merchants and property owners as our downtowns are becoming revitalized.
Our waterfronts in Campbellford and Hastings continue to improve each year. The purchase and removal of the old trailer park in downtown Hastings has complimented the Marina which is a huge economic driver for Hastings. Council’s commitment to the Marina has lead to a growing and successful attraction. Council’s business principles and strategies, along with dedicated Hastings community volunteers are the backbone of this municipal facility. The revitalization of downtown Hastings is paramount for me, as I see it as “the next big thing”.
The following partial list of infrastructure improvements is an example of what has been accomplished during the past seven years I have served you as Mayor. Although many of the projects we have achieved may not be important to all residents, they are individualy important for the residents who live near them. As I mentioned, the following list is a partial list, and yet it is long and perhaps not very interesting to read. It does show however, where some of your property tax dollars have been invested.
Transportation Infrastructure Rehabilitation
In Trent Hills, we have an inventory of 535 kilometres of roads of which 254 Km’s are gravel, 232 Km’s are surface-treated (tar and chip) and 48 Km’s are asphalt.
- 42 Bridges
- 78 kilometres of sidewalks
Campbellford / Seymour Ward
Campbellford
- Trent Dr. Reconstruction, Grind Asphalt, Base Stabalization, A Gravel, Pave, Speed Reduction (2010)
Seymour
- Bannon Rd. County Rd 35 to 5th Line West, Reconstructed and Resurfacing (2005)
- Baymeadows Subdivision, All Roads, Resurfacing (2006)
- Bradley Bay Rd. County Rd. 8 to James Rd. Resurfacing (2008)
- Burnbrae Rd. Pethericks Rd. to Nelson Hill, 1.8 Km’s, Resurfacing (2007)
- Burnbrae Rd. Pethericks Rd. to .6 Km’s, Resurfacing (2008)
- Cedar Shores Rd. Trent River Rd. to Turnaround, Resurfacing (2009)
- Crowe Bay Heights, All Roads, Resurfacing (2008)
- Crowe River Rd. 10th Line East, to 11th Line East, Resurfacing (2007)
- Crowe River Rd. 13th Line East, to .7 Km’s South, Resurfacing (2007)
- Crowe River Rd. County Rd. 38 to 10th Line, Resurfacing (2009)
- Green Acres Rd. County Rd. 8 to .8 Km South, Gravel A & B, Resurfacing, Double Coat (2008)
- Green Acres Rd. County Rd. 8 to 2nd Line East, Resurfacing (2010)
- IXL Rd. Church St. 1.8 Km North, Pulverized, A Gravel, Resurfacing, Double Coat (2009)
- Johnson Rd. 10th Line West to Turnaround, Resurfacing (2005)
- Lakeview Dr. County Rd. 50 to Turnaround, Resurfacing (2010)
- Mahoney Rd. 5th Line West to 1.6 Km’s South, Resurfacing (2007)
- Menie Rd. Burnbrae Rd. to 5th Line East, Resurfacing (2006)
- Morningside Dr. Trent River Rd. to Viewmont Ave. Resurfacing (2008)
- Myers Island Rd. County Rd. 30 to Hillside Dr. Resurfacing (2007)
- Petherick’s Rd. County Rd 38 to 8th Line East, Brush, Grub, Ditch, Subexcavate, A&B Gravel, Resurface X 2 (2004-5)
- Petherick’s Rd, County Rd. 38 to 8th Line East, Resurfacing (2010)
- Thomson Rd. Burnbrae Rd. to 7th Line East, Brush, Grub, Ditch, Subexcavate, A & B Gravel (2004-5)
- Trent River Rd. Lowered Turpin Hill (2004)
- Trent River Rd. Trillium Dr. to .9 Km’s West, Resurfacing (2004)
- Trent River Rd. County Rd. 50 to FF# 1426, 2.8 Km’s, Resurfacing (2006)
- Trent River Rd. Trillium Dr. to Morningside Dr. Resurfacing (2008)
- Trent River Rd. Lucky Strike Rd. to Cedar Shores, Pulverized, Ditch, Culverts, A Gravel Resurface, Double Coat (2010)
- Trent River Rd. Reynolds Rd. to Franklin Rd. Pulverised, Ditch, Culverts, A Gravel, Resurfacing, Double Coat (2010)
- Victoria St. 6th Line West to Corner, Resurfacing (2004)
- Riverside Blvd. Hillside Dr. to Hillside Dr. Resurfacing (2005)
- Rylstone Rd, Allans Mills Bridge to St. Marks Rd. Resurfacing (2004)
- Rylstone Rd. County Rd. 38 to FF# 416, 2 Km’s, Resurfacing (2006)
- Rylstone Rd. Corner North of St. Marks Rd. Resurfacing, Double Coat (2010)
- Wingfield Rd. County Rd. 38 to Maple Rd. Resurfacing (2004)
- Wingfield Rd. Rawdon 8th .3 Km North, Resurfacing, Double Coat (2009)
- 2nd Line East, Green Acres Rd, to Water St. Resurfacing (2005)
- 5th Line East, in Menie, .5 Km’s, Resurfacing (2006)
- 6th Line West, Victoria St. to Bannon Rd. Brush, Grub, Subexcavate, Gravel A & B, Resurfacing X 2 (2006)
- 7th Line East, Pethericks Rd. to .9 Km’s East, Resurfacing (2004)
- 7th Line East, County Rd. 38 to Thomson Rd. Resurfacing (2004)
- 7th Line East, Thomson Rd. to 2.5 Km’s East, Resurfacing (2007)
- 7th Line East, County Rd. 38 to Thomson Rd. Pulverise, Ditch, A & B Gravel, Resurfacing, Double Coat (2008)
- 8th Line East, FF# 2150 to FF# 2264, .5 Km’s, Resurfacing (2005)
- 8th Line East, Pethericks Rd. to .3 Km’s West, Reconstruction and Resurfacing (2007)
- 8th Line East, Thomson Rd. to 1.3 Km’s East, Resurfacing (2007)
- 10th Line West, County Rd. 50 to Johnson Rd. Resurfacing (2005)
- 10th Line West, County Rd. 30 to 3 Km’s West. Resurfacing (2005)
- 11th Line East, Rylstone Rd. to Kings Grant Rd. Resurfacing (2004)
- 11th Line East, Rylstone Rd. to 1.3 Km’s West, Resurfacing (2006)
- 11th Line West, IXL Rd. to 2.3 Km’s West, Resurfacing (2007)
- 11th Line West, County Rd. 50 to IXL Rd. Brush, Grub, Subexcavate, A & B Gravel, Resurfacing X 2 (2008)
- 12th Line East, County Rd. 50 to Crowe River Rd. Resurfacing (2006)
- 12th Line West, County Rd. 30 to Edgar Rd. Resurfacing (2005)
- 13 Line East, Stanwood to Allans Mills. Reconstructed, Ditch, Culverts, Gravel, Resurfacing, Double Coat (2003-4)
- 13 Line East, County Rd. 50 to Allans Mills Resurfacing (2010)
- Friendly Acres Rd. Concession 13 East to 4.3 Km’s North, Resurfacing (2005)
Hastings Ward
- Bay St. Extension (Princess St.) Construction and Resurfacing (2004)
- Bay St. Total Reconstruction and Pave a section, Storm (2010)
- Bridge and Front St. Intersection, Paving (2007)
- Bridge St. Headrace, Total Reconstruction and Paving (2007)
- Division St. Victoria St. to .2 Km West, Resurfacing (2009)
- Division St. Victoria St. to Top of Water Tower Hill, Reconstruction and Surface-treat (2010)
- Elgin St. Queen St. to Bay St. Resurfacing (2006)
Warkworth / Percy Ward
Warkworth
- Banta Rd. Water Plant to bottom of hill, Resurfacing (2005)
- George St. Reconstruct and Resurface (2010)
- Main St. Partner in The Main St. Revitalization Project. Total Reconstruction, Pave, Street Lighting (2004)
- Norham Rd. Hill at Concession St. West. Reconstruct and Pave (2005)
- Old Hastings Rd. Total Reconstruction, Water, Sewer, Storm, Curb and Gutter, Sidewalks, Pave (2008)
- Percy St. Total Reconstruction, Water, Sewer, Storm, Curb and Gutter, Sidewalks, Pave (2008)
- West St. County Rd. 25 to County Rd. 29, Resurfacing (2008)
- West St. County Rd. 29 to Dominion St. Resurfacing (2009)
Percy
- Autumn Rd. County Rd. 25 to Turnaround, Resurfacing (2008)
- Birchwood Crt. 8th Concession to Mapledean Dr. Resurfacing (2008)
- Campbell Rd. County Rd. 24 to 3rd Concession, Resurfacing (2004)
- Dudley Rd. Norham to corner, .3 Km, Resurfacing (2008)
- Dudley Rd. Norham Rd. .2 Km East, Resurfacing (2009)
- Faux Rd. County Rd. 35 to Concession Rd. 11, Resurfacing (2005)
- Glover Rd. County Rd. 29 to 1.5 Km’s, Resurfacing, Double Coat (2008),
- Glover Rd. County Rd. 29 to McCubbin Bridge, Pulverized, A Gravel, Resurfacing, Double Coat (2009)
- Godolphin Rd. 8th Concession to 9th Concession, Resurfacing (2004)
- Godolphin Rd. Percy St. Hill to Greenly Rd. Reconstructed and Resurfacing (2005)
- Godolphin Rd. County Rd. 35 to 9th Concession, Resurfacing (2009)
- Godolphin Rd. Concession 6 to Crestview Rd. Resurfacing (2010)
- Gravel Rd. County Rd. 25 to Norham, Resurfacing (2007)
- Grant Rd. County Rd. 25 to Gravel Rd. Resurfacing (2007)
- Greenly Rd. Godolphin Rd. to Bridge, Resurfacing (2004)
- Honey Line, County Rd. 25 to 2.7 Km’s, Resurfacing (2006)
- Hurlbut Cres. Winter Rd. to Turnaround, Resurfacing (2008)
- Jackson Rd. Marine Dr. to end, Resurfacing (2007)
- Lakeshore Rd. Trentwood to end, A Gravel, Resurfacing, Double Coat (2004)
- Lawson Dr. Godolphin Rd. to end, Resurfacing (2008)
- Linton Rd. County Rd. 24 to Sandy Flats Rd. Resurfacing (2004)
- Maidens Mill Rd. Godolphin Rd. to Turnaround, Resurfacing (2008)
- Mapledean Dr. 8th Concession West, to Turnaround, Resurfacing (2008)
- Marine Dr. Concession Rd 11 to the end, Resurfacing (2007)
- Newman Rd. County Rd. 25 to Gravel Rd. Resurfacing (2005)
- Norham Rd. County rd. 29 to Norham Intersection, Resurfacing (2005)
- Norham, (Village) All Roads, Resurfacing (2008)
- Pine Crt. Godolphin Rd. to Turnaround, Resurfacing (2008)
- Platt Rd. Gravel Rd. to Boundary, Resurfacing (2009)
- Rusaw Line County Rd. 45 to 11th Concession West, Resurfacing (2006)
- Sandy Flats Rd. Repair from 2003 Resurfacing (2004)
- Sandy Flats Rd. Linton Rd. to Boundary, Resurfacing (2005)
- Sandy Flats Rd. Linton Rd. to 2.9 Km’s, Resurfacing (2007)
- Skinkle Rd. N, Beaver Rd. to Mahoney Rd. Brush, Grub, Subexcavate, Gravel A & B (2003)
- Skinkle Rd. S, County Rd. 29 to 1.7 Km’s North, Resurfacing (2007)
- Smith Rd. County Rd. 35 to 11th Concession 11 East, Resurfacing (2007)
- Spring Lane, County Rd. 25 to Turnaround, Resurfacing (2008)
- Trentwood Estates, All Roads, Resurfacing (2006)
- Ward Rd. 8th Concession to 1 Km, Resurfacing (2008)
- Ward Rd. 8th Concession West to Homestead Rd. Pulverized, Ditch, A Gravel, Resurfacing, Double Coat (2010)
- Water St. Two Sections (Percy Con 13th E) Reconstruction and Resurfacing (2007)
- Water St. (Percy Con 13th E) Marine Dr. to 2.5 Km’s West, Resurfacing (2010)
- Winter Rd. County Rd. 25 to Bagley Rd. Resurfacing (2008)
- 2nd Concession East, County Rd. 30 to Platt Rd. Resurfacing (2006)
- 3rd Concession West, Campbell Rd. to top of Banta Rd. Hill, Resurfacing (2004)
- 3rd Concession West, Campbell Rd. to Gummow Rd. Resurfacing (2007)
- 3rd Concession West, Stone Rd. to Bulls Rd. Resurfacing (2005)
- 3rd Concession East, Gummow Rd. to Stone Rd, Pulverise, Culverts, A Gravel, Resurfacing, Double Coat (2004)
- 3rd Concession East, Gummow Rd. to Stone Rd. Resurfacing (2009)
- 4th Concession, County Rd. 25 to Campbell Rd. Resurfacing (2004)
- 6th Concession East, Greenly Rd. to 1.5 Km’s West. Ditch, Culverts, Gravel, Resurfacing, Double Coat (2003)
- 6th Concession, Greenly Rd. to Beaver Rd. and Godolphin Rd. to MacDonalds, Resurfacing (2006)
- 8th Concession West, Richardson Rd. to Ward Rd. Resurfacing (2005)
- 8th Concession West, County Rd. 25 to County Rd. 45 (2010)
- 9th Concession West, County Rd. 45 to Boundary, Resurfacing (2008)
- 11th Concession East, (The Dutch Line) County Rd. 25 to 4.2 Km’s East, Resurfacing (2006)
- 11th Concession West, Top of hill to end. 3.1 Km’s, Resurfacing (2006)
- 13th Concession East, Marine Dr. to 2.5 Km’s West, Pulverise, Subexcavate, Ditch, Brush, Culverts, Gravel A&B,
- Resurfacing, Double Coat (2007)
- 13th Concession East, Marine Dr. to 2 Km’s East, Pulverise, Subexcavate, Ditch, Brush, Culverts, Gravel (2009)
Roads Raised Due To Flood Potential
- Muskie Mile Lane (2010)
- 1st Line East (2009)
- 2nd Line East (2009-10)
- Izumi Way (2009-10)
- Laguna Rd. (2009)
-
River Rd. East and West (2009)
Bridges
- New Bridge on Main St. Downtown Warkworth (2004)
- New McCubbin Bridge Con Rd 4 E. Percy (2007)
- New Gummow Bridge on Gummow Rd. Percy (2010)
- New Hayes Bridge 7th Line East. Seymour (2010)
Sidewalks
Our very successful and ongoing sidewalk replacement program has resulted in more than five kilometres of sidewalk being replaced and upgraded to current standards during my 7 years as your Mayor. Our new sidewalks are wider to allow accessibility vehicles to pass each other.
Critical Infrastructure
- Completion of the Campbellford Water Plant Upgrades (2004)
- Completion of the Hastings Water Plant Upgrade (2004)
- Completion of the Warkworth Water Plant Upgrades (2004)
- Completion of the Cast Iron Water Main Replacement Program (2006)
- New Cast Iron Water Main Replacement Program in place and engaged (2007)
- Planning for major repairs to Water Tower, Campbellford (2009)
- Bridge St. Watermain Replacement Project and Pave, Hastings (2007)
- Major Watermain Replacement Project In Hastings (2010)
- Second Watermain River Crossing Environmental Assessment, Hastings (2009)
- Complete Retrofit of Wastewater Plant in Campbellford (2008)
- Complete Retrofit of Wastewater Plant in Warkworth Hastings (2009)
- Hastings Water Main Project (2010)
Water and Sewer Separation and Street Upgrades
Total Reconstruction, Water, Sewer, Storm, Curb & Gutter, Sidewalks, New Pavement
Campbellford
- Booth St. North (2004)
- Canrobert St. (2010)
- Churchill Dr. (2005 & 2010)
- Cockburn St. (2005)
- Doxsee Avenue North (2008)
- Elmore St. (2005)
- Garry St. (Lower) (2010)
- Hillcrescent (2005)
- Isabella St. (2010)
- Ireton St. (2005)
- Kent St. (2005)
- Leonard’s Lane (2009)
- Front St. South (2008)
- Front St. North (2009)
- Major St. (2010)
- Maple St. (2005)
- Margaret St. (2005)
- Market St. (2008-9)
- Naseby St. (2005)
- Oliver Rd. (2010)
- Queen St. (2008)
- Richard St. (2010)
- River St. West (2008)
- Wellington St. (2005)
Business Park Expansion
- New Business Park sign installed (2005)
- Heliport Rd. extended from Industrial Dr. to 5th Line W (2010)
- New water and sewer installed in Heliport Rd. (2010)
- Stormscepters and oil/grit seperators installed (2010)
- 5th Line West, upgraded to municipal standards (2010)
Municipal Parks and Outdoor Recreation
Pool
- Easy access steps (2004)
- New diving board (2005)
- Total excavation, piping, and new deck (2006)
- New accessible lift (2008)
- New accessible washrooms (2008)
Parks
-
Reconstructed two soccer fields at Kennedy Park Campbellford (2009)
- Constructed new Parking lot at Kennedy Park Campbellford (2009)
- Constructed new Skateboard Park in partnership with the SK8 Park Committee, Campbellford/Seymour Community Foundation, and many community contributors at Kennedy Park Campbellford (2009)
- Total electrical re-wiring of Old Mill Park and waterfront in Campbellford (2008-09)
- Assumed Crowe Bridge Park into municipal operations (2010)
- Total playground equipment replacement at the Ed Brownlee Memorial Park in Hastings (2010)
- Three new playgrounds, each with an adult fitness park in partnership with the Let them Be Kids Foundation, the Campbellford/Seymour Community Foundation, the Hastings Youth Action Committee, and many
- community contributors (2010)
- Our Soccer Fields have been well maintained and we have been fortunate several community residents have helped with the restoration of some of them.
- Reconstruction of small soccer fields, and parking lot for the new skate-park. Kennedy Park (2008)
Arenas
The following items are a list of major upgrades only.
Campbellford-Seymour Arena
- New Dehumidifier (2003)
- New Zamboni ice re-surfacing machine (2004)
- New chilling unit (2004)
- New dehumidifier (2005)
- New glycol closed cooling loop (2005)
- New dasher boards and glass (2006)
Hastings Arena
- New chilling unit (2004)
- New chilling unit and condenser (2003)
- New electric heaters and water tanks (2005)
- New piping header (2005)
Warkworth-Percy Arena
- Roof painting at Percy Arena (2004)
- New condenser (2005)
- New dehumidifier (2008)
- New dasher boards and glass (2008)
- New doors and gates (2009)
- New flooring (2009)
- New netting (2009)
- New header trench cover (2009)
- New roof (2010)
- New siding (2010)
- New HVAC system (2010)